Immagine della notizia

Power utility built $95 million 500-megawatt power substation for Intel's $100 billion Ohio fab, but six-year delay leaves substation capable of powering 500,000 homes idle

Date: 2025-06-23 15:05:30

Intel has once again postponed the launch of its Ohio chip plant, which is now expected in 2031, leaving utility AEP Ohio with an idle $95 million substation.


Sources:

Click and go !